SRH Law – Saunders | Raubvogel | HandSRH Law – Saunders | Raubvogel | Hand

Making a difference is our practice.

  • Our Difference
  • Practice Areas
  • Our Team
  •  
  • Careers
  • Contact Us
  • News

Legislative Report on Vermont’s Environmental Permitting – Potential for Dissolution of Environmental Court and Natural Resources Board

For the past year, at the direction of Governor Shumlin and with the support of the General Assembly, the Natural Resources Board (NRB) and the Agency of Natural Resources (ANR) have been engaged in reviewing the state and municipal environmental permitting processes in Vermont and developing suggestions for improving these processes. The review has included focus group meetings and public meetings to elicit feedback regarding the strengths and weaknesses of the current permit systems, as well as ideas for changes that could improve the permit systems. The Natural Resource Board’s website has devoted a page to this process, which includes a list of the focus group and public meetings held and links to comments received. Recently, as a culmination of this initial review and public outreach effort, the NRB and ANR issued a joint report to the General Assembly.

The legislative report shows that the NRB and ANR examined several distinct areas of environmental permitting in Vermont: state Act 250 permits, which are administered by the NRB; state air, water, waste, and other permits that are administered by ANR; and municipal land use permits, which are regulated and administered by individual towns and cities with minimal state statutory guidance. These various permit processes are quite different in terms of the initial permit application and review processes, but they follow a common path on appeal, which is to undergo de novo review at the Vermont Superior Court, Environmental Division (Environmental Court). (Appeals of land use or zoning permits are on-the-record appeals only in those municipalities that have adopted the municipal administrative procedures act and follow a development review board process. According to the report, only ten municipalities have done so.) The report identifies the appeal process as a main area of focus because, although there is a relatively low percentage of appeals, the appeal process is seen as taking the greatest amount of resources—including time—for permit applicants, permit opponents, and the state.

The report explores two possible approaches to improving the appeal process, but stops short of specifically recommending either of the two approaches as the best way forward. The changes contemplated are either (1) adjusting the current Environmental Court process, or (2) creating a new quasi-judicial environmental review board. While the report avoids making any explicit statements to this effect, the role and duties that the environmental review board is contemplated to undertake would make it possible to dismantle both the Environmental Court and the NRB itself.

According to the report, public comments and focus group feedback indicate that the current Environmental Court process and proceedings are difficult to navigate for parties who are not represented by legal counsel, and that it takes too long to receive a final decision from the court. To address these issues, the first proposed solution would make certain changes to the current framework of the Environmental Court, including:

  • addition of hearing officers or magistrates to assist the two Environmental Court judges
  •  limitations on the scope or extent of discovery
  • encouraging the use of prefiled testimony and exhibits instead of relying entirely on live hearings for the submission of evidence
  •  creation of a public advocate to serve two possible roles: (1) represent the public interest in environmental matters, similar to the role of the Department of Public Service in utility matters; (2) serve as a low-cost or no-cost provider of legal assistance for unrepresented parties, similar to Legal Aid
  • use Alternative Dispute Resolution (ADR) more effectively by having a case manager, hearing officer, or judge evaluate cases and decide when ADR is likely to assist in settling matters; using other forms of ADR aside from mediation

The second proposed approach would scrap the Environmental Court entirely, and replace that system with a new permit appeal process before a professional review board (Board). As described in the legislative report, the Board would be similar to the Public Service Board, which regulates Vermont’s utilities and energy producers. The report describes the Board as a three-member panel with two alternate members, all of whom would be selected through a process like that used for Public Service Board members or Superior Court judges, with appointment by the governor and confirmation by the Senate. As with the Public Service Board, the Board members would serve fixed terms with staggered term periods to provide a balance between continuity and new appointments. The report proposes that the Board would have essentially the same appellate jurisdiction as the Environmental Court, original jurisdiction over enforcement matters, and an additional role in that the Board would have original jurisdiction over the initial permit review for complex projects of great public interest. However, instead of operating like the Environmental Court, the report recommends that the Board operate in a manner similar to the Act 250 District Commissions in terms of the discovery process, use of prefiled testimony, and the administration of hearings. The report states that the District Commissions were widely recognized as effective venues for environmental decisions and were accessible to the public and unrepresented parties.

Because the Board’s jurisdiction would encompass all areas that the Environmental Court currently covers, and would have even broader original jurisdiction over some initial permit proceedings, there would no longer be a role for a separate Environmental Court. The report also states that the Board could take over the rulemaking and support duties that the Land Use Panel of the NRB currently performs for Act 250 matters. Further, the report recommends moving the rulemaking responsibilities of the NRB’s Water Resources Board to ANR. Based on these recommendations, it seems that creation of the Board would also allow for dissolution of the NRB, as all of its current roles and responsibilities would be transferred to the Board and ANR.

One further major change to the permit appeal process, which the report indicates could be implemented in either the Environmental Court or the Board model, is to change from a de novo review standard to an on-the-record review standard in more of the appeals. The Act 250 permit process seems largely equipped to handle this change at the present time giventhe manner in which the District Commissions currently operate. However, ANR would have to make substantial changes to its permit application review and approval procedures in order to allow for record review of its permit decisions. Similarly, most municipalities would need to adopt uniform administrative procedures, such as the Municipal Administrative Procedures Act, to ensure that their decisionmakers were fully trained and well-advised in proper procedural rules and to ensure that a proper record is created in order to allow for record review of their land use decisions.

In addition to these possible changes to the permit appeal processes, several other changes to the environmental permitting framework are discussed in the report. These include, as indicated above, transferring the water quality rulemaking responsibility from the NRB’s Water Resources Panel to ANR. Other ideas discussed include giving greater weight to ANR-issued permits and municipal permits in satisfying Act 250 criteria; increasing the use of professional certification to satisfy the applicant’s burden for ANR permits; increasing the use of on-line forms and permit application submissions for ANR permits; increasing the scope of public notice of ANR permit applications and draft permits; standardizing the notice and comment periods across all ANR permits; and increasing public participation in the ANR permit process prior to the time that ANR issues a draft permit.

Most of the possible changes described above would require legislative action, so readers interested in these issues should watch the current session for more developments. Governor Shumlin specifically requested the General Assembly to take action to implement “on the record” review for Act 250 appeals in his recent budget address —indicating a priority for action on that item.

The NRB is accepting comments on the legislative report through its web page dedicated to this project.

Facebooktwitterlinkedin

Eileen Elliott appears on Common Good Vermont

SRH Law’ very own Eileen Elliott appears on Common Good Vermont to speak on the fiduciary and stewardship obligations of non-profit board members and directors.

Drawing from both her legal experience and time spent serving on various non-profit boards, she explains the three legal duties assigned to board members by Vermont’s non-profit corporation statute – namely, the Duty of Care, the Duty of Loyalty, and the Duty of Good Faith.  She goes on to detail how these are relevant to the individual board member as well as addressing other key issues faced by boards and their members in the non-profit sector and beyond.

 

Facebooktwitterlinkedin

“Beginning Construction” Requirements for Section 1603 Cash Grants for Renewable Energy Projects

The federal Section 1603 Treasury Grant Program has provided a major incentive for the development of renewable energy projects in recent years by allowing owners of such projects to receive a cash grant in lieu of federal tax credits for specified energy property.  The U.S. Department of the Treasury reports that it has paid out $8.5 billion to approximately 18,000 Section 1603 grant applicants to date.

The program was originally set to expire last year, but it was extended so that projects that will be placed in service by the end of 2011 are eligible for the grant.  Additionally, projects that have begun construction by the end of 2011 and will be placed in service by 2012 (wind), 2013 (most other renewables), or 2016 (solar), can take advantage of the program.  With the “begin construction” date fast approaching, it is important for renewable energy developers to understand how to ensure that they will be eligible for Section 1603 grants.  Some of the important factors needed to meet the Treasury Department’s requirements for beginning construction are summarized here.

There are two separate and independent ways that an applicant for a Section 1603 grant can establish the beginning of construction:

1)      Physical work of a significant nature, or

2)      5% “safe harbor” of costs paid or incurred

The physical work of a significant nature method of establishing that construction has begun has the following constraints/limitations:

–          The physical work must take place on “energy property”—this means the property that is integral to the production of energy.

  • Transmission equipment does NOT count as energy property.
  • Generally, the Treasury Department will include all interconnection equipment, including the step-up transformer, as energy property.
  • Everything on the transmission side of the step-up transformer will be considered transmission equipment, not specified energy property.
  • Most road building will not count as “energy property,” but each project is scrutinized on an individual basis and some roads could qualify as energy property.

–          The physical work must be part of a “continuous program of construction” and Treasury puts particular emphasis on continuity.

  • Unplanned work stoppage that is out of the control of the owner/contractor is acceptable.
  • The Treasury Department’s examination will be on what kind of work continuity is expected for a project of its type, in the location where the project is being built—winter or other weather-related work stoppages can be acceptable.

–          The work includes work done by a contractor, as long as it is done pursuant to a binding written contract, legally enforceable under state law, with damages not less than 5% of the total contract.

  • It is important that the contract is in place before work is commenced.

The physical work of a significant nature method also has the following flexibility:

–          There is no minimum amount of work that must be complete by the end of 2012; the work can be very minimal because the emphasis is on the continuity of the work.

–          The work need not take place at the project site; indeed, no site need even be identified for the project under this approach.

The 5% Safe Harbor method of establishing the beginning of construction focuses on the actual expenditures made by the applicant, and it requires that the applicant:

–          has paid or incurred 5% of the total actual costs of specified energy property.

–          meets the “economic performance rule” from Section 461(h) of the tax code – this means that the applicant has to actually make the payment and reasonably expect to receive the property within 3½ months.  

  • “Receiving” or being “provided” the property can mean delivery, acceptance, or the passage of title of the property, but the applicant must use the same method throughout the term.
  • Making a deposit on the property is NOT sufficient to count toward the 5% safe harbor.

–          incurs any contract-based costs pursuant to a binding written contract, legally enforceable, with damages not less than 5% of the total contract.

–          possibly needs to have a project site identified (this issue is not entirely clear under current U.S. Treasury guidance).

The 5% safe harbor method also has the following flexibility:

–          Costs/contracts may be for services, not just goods.

–          There is no need to build/construct anything.

–          There is no continuity requirement.

–          “Off-the-shelf” items qualify towards the 5% of costs (but note that purchases of extended warranties do NOT count toward the 5%).

–          There is a special “look through” rule that can be used to meet the economic performance rule for the applicant:

  • if the applicant’s supplier meets the economic performance rule, then this can be attributed to the applicant.

Potential Section 1603 applicants should also be aware that the date for beginning construction is December 31, 2011, and applications for projects that will begin construction but will NOT be placed in service by the end of 2011 must be submitted by September 30, 2012.

Developers should also keep in mind that Section 1603 grants are available for expansion of existing projects, as long as there is additional capacity being provided at the facility.  Even if a Section 1603 grant was used for the original facility, the developer can still be eligible for an additional grant if additional capacity is being created.

The Treasury Department emphasizes that the completeness of an application by the final date is of paramount importance, and applicants should make use of the Section 1603 website and associated checklists (click here for the checklist for properties that have begun construction, but not been placed in service) and other guidance (click here for guidance as most recently revised in April 2011) to ensure that they understand all application requirements.

Disclaimer:  As with all of our blog posts, this is not legal advice.  Every situation regarding Section 1603 eligibility is fact-specific and would need to be treated on a case-by-case basis.  No decisions should be made based on the information contained in this blog post alone.  Readers are encouraged to make sure they have gathered all relevant information and to contact an attorney to discuss their specific situations.

Facebooktwitterlinkedin

Act 250 Criteria: Not Applicable? Not Your Decision, Environmental Court Says

In a Jurisdictional Opinion issued earlier this year, the Vermont Environmental Court made clear that Act 250 applicants do not have the independent authority to determine which criteria might not apply to their permit application.

The case – In re Jurisdictional Opinion # 6-007: Wright Parcel Act 250 Subdivision, McBride Parcel Act 250 Subdivision Docket Nos. 55-4-10 Vtec & 56-4-10 Vtec (Feb. 23, 2011) – involved an appeal by Act 250 applicants regarding whether their Act 250 subdivision applications were complete.  Although the appeal has no bearing on any of the substantive Act 250 criteria, the decision is useful to any Act 250 applicant in that it spells out some of the basic requirements for ensuring that an application is complete when filed with the District Commission.

The issue in this case was whether the District #6 District Coordinator erred in rejecting the Act 250 applications as incomplete where the applicants had stated, under several criteria, that the criteria were “not applicable” because the subdivision would not affect the resources or characteristics protected by the criteria.  The Environmental Court ruled that it is the District Commission’s role to determine which criteria are applicable to any given permit application, and it is the applicant’s responsibility to provide the commissioners with sufficient information for them to make the determination.  Thus, the District Coordinator correctly rejected the applications as incomplete.

In this case, the applicants were proposing to subdivide two parcels of land into three lots per parcel.  The District Coordinator ruled that the applications were incomplete because under Criterion 9(B) (the primary agricultural soils criterion), the applications stated, “Criterion 9(B) does not apply to this application as no impact to any soils, primary agricultural or not, will occur due to the subdivision or sale by auction as no earth disturbance or construction of any kind is proposed as part of this application.”  After submitting these applications, the applicants later provided additional information about the agricultural soils on the parcels, including maps and a letter from the Department of Agriculture.  Additionally, the applicants also obtained state wastewater and potable water supply permits for each of the proposed subdivisions.  These permits were sent to the District Coordinator, and after receiving them, the District Coordinator believed that the Act 250 applications were intended to request approval for construction of houses, not simply for subdivision of the parcels.  The District Coordinator then requested additional information from the applicants.  The applicants met with the District Coordinator to discuss some of these issues and explain that they were seeking permits solely for subdivision, and that they were not planning to construct any houses themselves.  They also discussed the possibility of the District Coordinator reconsidering the decision that the applications were incomplete and the request for additional information; however, instead of formally requesting that the District Coordinator reconsider, the applicants appealed the decisions to the Environmental Court.

In its decision, the standard that the Environmental Court used was whether the applications provided “enough information about the property and its resources and characteristics to allow the District Commission to determine whether resources on the land must be assessed or analyzed under the Act 250 criteria for the project property as a whole, before the boundary lines are approved for the subdivision.”  The Court stated that, to decide the case, it was “necessary to determine which Act 250 criteria could potentially be affected by the proposed drawing of lot lines and sale of the lots separate from one another, without regard to what those lots might be used for by their purchasers.”  Because the Environmental Court has de novo authority in Act 250 appeals, it looked not only at the information provided to the District Coordinator at the time it decided that the applications were incomplete, but also at the information provided to the Court during the appeal.

Based on the information provided, the Court evaluated the Act 250 applications and determined that the applications were deficient under multiple criteria, including stormwater, floodways, wildlife and endangered species, primary agricultural soils, and earth resources.  Thus, the applicants were required to provide the additional information before their Act 250 applications would be reviewed by the District Commission.  The take-home message from this case for Act 250 applicants is to provide all of the information requested in the Act 250 application, and leave it to the District Commission to determine whether the criteria apply to the project or not.

Facebooktwitterlinkedin
  • « Previous Page
  • 1
  • …
  • 11
  • 12
  • 13

How can we help you make a difference?

Hiring an attorney is about finding someone you trust to advocate for you. We take our obligations to our clients seriously, and will do everything we can to help you succeed.

Contact Us »

Contact Us

91 College Street
PO Box 545
Burlington, VT 05402-0545

 

Email info@srhlaw.com

tel (802) 860-1003

fax (802) 860-1208

News

SRH Law is pleased to welcome Malachi Brennan as its newest partner

Megan Grove to participate in Common Good Vermont’s Nonprofit Management Certificate Program

SRH Law Sponsors Inaugural Justice Gala & Legal Services Vermont’s 30th Anniversary

Fighting the Fight without Jeopardizing your 501(c)(3) Status: Common Good Vermont Nonprofit Summit

SRH Law Sponsors Renewable Energy Vermont’s 2025 Annual Conference

More News »

Connect with Us 

  • Facebook
  • Instagram
  • LinkedIn
  • Twitter
Careers at SRH Law
Make Secure Online Payment
Privacy Policy & Terms of use
 

SRH Law

Copyright © 2026 SRH Law – Website by Stride Creative • Log in